The Dam Engineers Had to Build Twice: How Colorado Rebuilt a Lifeline Above Denver
High in the Rocky Mountains west of Denver, a concrete wall built in the 1950s is being reshaped into an entirely new structure. Engineers are raising Gross Dam so far beyond its original form that the project feels less like an upgrade and more like constructing a second dam on top of the first. The risks are enormous. If the engineering fails, the city could lose one of its most important water supplies. I stood near the site once and felt the weight of a project that has to succeed because the region cannot afford the alternative.
Why Denver’s Water Supply Reached a Breaking Point
Denver Water serves more than 1.5 million people across the Front Range, and the demand keeps climbing. Growth alone didn’t push the system to its limits. Water security across Colorado changed after a series of climate-driven shocks. The 2002 mega-drought exposed how fragile the region’s reservoirs had become. The Hayman Fire that same year, still one of the largest in state history, burned nearly 140,000 acres and left watersheds clogged with sediment for decades.
The pattern has continued. Snowpack swings sharply from year to year. Runoff arrives earlier as temperatures warm. Wildfires, including the Marshall Fire in 2021 and the East Troublesome Fire in 2020, reached populated areas that once felt protected. Every one of these events limits the reliability of mountain water systems designed for calmer decades.
The structural imbalance makes things harder. Nearly 90 percent of Denver’s stored water sits south of the city. Only a small share lies to the north. Gross Reservoir sits on that northern flank, and its limited size leaves the region exposed during drought cycles.
Denver needed a way to rebalance the system, and engineers began looking to the only reservoir positioned to solve part of the problem.
Also Read: Can Engineering Save the Maldives from Sinking?
A Reservoir Built With the Future in Mind
When Gross Dam was completed in 1954, its designers left clues about how they viewed the future. They built a concrete gravity dam that could be raised later if water demand grew. That kind of long-term foresight was rare at the time.
Gross Reservoir is fed by the Fraser River and receives diverted water from the Colorado River Basin through the Moffat Tunnel, a 9-kilometer passage that carries both trains and water beneath the Continental Divide. The dam was named for Dwight D. Gross, Denver Water’s chief engineer during the mid-century expansion, and his work now forms the foundation of a project unlike any other in the United States.
The region finally reached the moment he anticipated. Denver needed more storage, and Gross Reservoir was the only northern asset capable of growing.
How Much Bigger Colorado Needed to Build
The original structure held about 42,000 acre-feet of water. After years of review, the federal government approved a plan to nearly triple that capacity. Once complete, the expanded reservoir will store 119,000 acre-feet, or roughly 150 million cubic meters.
That additional supply equates to water for around 72,000 homes each year. To create that volume, engineers must raise the dam by 131 feet. The finished structure will stand 471 feet tall, making it one of the highest concrete dams in the country and one of the most complex dam-raise projects ever executed.
Increasing a dam’s height by more than a third is rare. Doing it at more than 7,000 feet above sea level adds another layer of difficulty.
Building a Higher Dam in Thin Mountain Air
Construction began in 2022, and crews faced some of the hardest working conditions in American civil engineering. At this elevation, weather shifts quickly. Storms can form within minutes. Temperatures drop sharply at night. The thin air slows heavy labor and makes concrete placement more demanding.
Engineers approached the raise as a series of 118 stepped lifts. Each four-foot layer steps back two feet as it rises, slowly turning the straight face of the old gravity dam into a curved arch capable of transferring immense water loads into the canyon walls. This shift in shape is historic. No other project has attempted to transform a gravity dam into an arch dam on this scale.
By June 2025, the new concrete had reached the height of the original crest. Old and new engineering met in a single line, a moment that showed the transformation was real.
The Concrete Behind the Engineering Breakthrough
The original dam used conventional mass concrete, poured in huge blocks similar to those at Lake Mead’s Hoover Dam. That technique would be far too slow for this project, and the heat generated by thick pours would create cracking risks.
The new structure uses roller-compacted concrete, or RCC. The material arrives in dump trucks, spreads across the dam face in thin layers, and compacts under the weight of heavy rollers. The process allows rapid placement and steady curing in cold mountain conditions.
The scale is staggering. The first dam contains roughly 600,000 cubic yards of concrete. The raise adds more than 700,000 cubic yards of RCC. No dam raise anywhere in the world has used this much roller-compacted concrete.
A Project With a Half-Billion-Dollar Price Tag
The budget approved in 2021 placed the total cost at $531 million. Denver Water planned the funding so that taxpayers would not shoulder direct costs. Instead, the utility relies on ratepayers, new system connection fees, and revenue from the hydropower plant that began generating electricity in 2007.
Even with careful planning, legal disputes pushed the project into unpredictable territory. Any delay raises costs when equipment, materials, and mountain crews are already mobilized.
The Court Order That Stopped Construction
In April 2025, a federal judge halted all work. The Waterkeeper Alliance, Sierra Club, and Save the Colorado argued that the US Army Corps of Engineers failed to fully examine basin-wide environmental impacts or evaluate reasonable alternatives.
For environmental groups, the ruling marked a major win. For engineers, it forced an abrupt shutdown at a critical phase.
Construction Restarts Under Limitations
One month later, the judge reversed the injunction. Leaving the dam partially raised posed its own risks to downstream communities. Work resumed quickly, but a major restriction remained. Denver Water could not fill the reservoir until further environmental reviews received approval.
Even with a completed dam, filling it could take five years or longer because annual snowpack and river flows vary widely. The timeline now depends as much on regulatory approval as on engineering progress.
A Project Shaped by Environmental Tradeoffs
Denver Water argues that the expansion will strengthen habitats through better stream flows, new wetlands, and protected open space. The utility has committed to long-term ecological restoration along South Boulder Creek and other affected areas.
Still, the environmental cost is significant. Construction required the removal of nearly 200,000 trees. Noise and traffic affect more than 1,000 nearby homes. Opponents point to a Colorado River Basin already strained by declining flows, with studies from the US Bureau of Reclamation showing long-term reductions of roughly 20 percent.
For critics, adding another major reservoir in a stressed watershed feels like a step in the wrong direction. For supporters, the project is a necessary safeguard as climate extremes become the norm.
Where the Project Stands Now
If construction stays on schedule, the dam will reach full height in 2026, with spillways and control buildings completed soon after. Filling could begin in 2027 if federal and state agencies grant approval.
There remains a real chance that the structure could stand finished yet remain unused for years. That uncertainty highlights the tension between engineering ambition and environmental oversight.
Also Read: These 90-Year-Old Bridges Could Cut Off Cape Cod — Here’s the $4.5B Fix
What This Dam Says About the Future of Water
The Gross Reservoir expansion pushes infrastructure to its limit. Engineers are stretching a mid-century design into a form never attempted before. Environmental advocates are pushing back against growth that relies on taking more water from stressed river systems. Regulators are navigating a landscape where every major project faces intense scrutiny.
The dam has become more than a reservoir project. It represents a test of how cities adapt to a future shaped by drought, wildfire, and unpredictable climate behavior. You can see it as a necessary investment in resilience or as a warning that the region is running out of easy answers.
Either way, Gross Reservoir now stands as one of the most complex water projects in modern Colorado history, a reminder that securing water in the West demands engineering strength, ecological awareness, and the patience to build a lifeline twice.